Add Test Verification Gate

A gate is an access point that allows you to stop the pipeline to automatically go to the next stage. A gate helps you to manually intervene and verify or approve a stage of the pipeline before moving on to the next stage in the sequence. Adding a Gate in ISD allows you to either automate your pipeline based on data from supported data sources.

There are four types of gates you can add:

  • Approval

  • Verification

  • Test Verification

  • Policy

Test Verification Gate

An approval gate stops the pipeline and waits for approval either from a human user or from a computer based on data from a supported plugin.

You can add a Test Verification Gate after creating a pipeline to the application. To add a Test Verification Gate follow the steps below:

If you haven’t created an application already, click here.

If you haven’t created your pipelines yet, click here.

  1. From the Application dashboard, select your application name which you need to edit a pipeline. Click "Three dots" at end of the application name and then select "Edit Pipeline" as shown in the image below.

    Add_test_verification_gate1

  2. It will redirect you to the "Pipeline Builder" page, where you can modify your pipeline by selecting it from the left-hand side. Users can modify the available pipeline within the application as shown below.

    Add_test_verification_gate2

  3. Select your pipeline, where you need to add the Test Verification Stage. Click "Add Stage" and then select the type "Test Verification" from the drop-down menu as shown in the image below.

    Add_test_verification_gate3

  4. Next, you get the option to configure the Test Verification gate as shown in the image below:

    Add_test_verification_gate4

  5. Update the Test Verification configuration attributes as described below on the above screen and click "Save Changes"

    • Gate URL: Please enter the Gate URL

    • Life Time Hours: Please enter the Life Time in Hours like 0.5

    • Minimum Canary Result: Please enter the Minimum Canary Result

    • Canary Result Score: Please enter the Canary Result Score

    • Log Analysis: Please Enable Log Analysis with true / false

    • Baseline Start Time: Please select Baseline Start Time

    • Canary Start Time: Please select Canary Start Time

    • Test Run Key: Please enter the Test Run Key

    • Baseline Test Run Id: Please enter the Baseline Test Run Id

    • New Test Run Id: Please enter the New Test Run Id

    • Test Run Info: Please enter the Test Run Info

    • Gate Name: Please enter Gate Name that is created in OES

    • Image Ids: Please enter the Image IDs